Carlsbad's permit-ready ADU plans are offline. What now?

Posted Oct 14, 2026

If you've read anything about building an ADU in Carlsbad, you've probably seen the city's Permit-Ready ADU Program: pre-approved detached one-story plans in four sizes (studio, one, two and three bedrooms) and three styles (Spanish, Farmhouse and Modern). The city's own ADU page estimates they save 3 to 6 months and about $8,000 to $16,000 in design fees.

There's a catch that most contractor sites haven't caught up with. When we checked the city's Permit-Ready ADU Program page on October 14, 2026, it said the plans are being updated to meet the 2025 California Building Codes and are currently unavailable. The city had projected they'd be back by summer 2026. As of mid-October, they weren't.

Why the plans were pulled

Building codes in California update on a three-year cycle, and the 2025 code took effect at the start of 2026. Pre-approved plans are only useful if they comply with the code in force when you apply, so the city has to update them. That's routine. The timing just hasn't matched the city's estimate.

Your options while you wait

1. Design a custom ADU now

A custom plan costs more up front in design, but it can be shaped to your lot, match your house's exterior exactly (which IB-111 requires anyway), and use any height or size exception that applies to your parcel. The city plans are single-story detached units, so if you want an attached ADU, a second story, or an ADU over a garage, custom design was always the route. See ADU design in Carlsbad.

2. Use a factory-built unit

HCD-certified manufactured homes can be ADUs in Carlsbad, and modular units built to code are permitted like any ADU. Park model trailers can't be. You still need a full building permit, a site plan, foundation and utilities. See prefab and modular ADUs.

3. Do the site work on paper now

Even with a pre-approved plan, the city still needs a site-specific submittal. Survey, utility locations, Coastal Zone status, transit walking distance and lot coverage all have to be worked out regardless. Doing that now means you're ready to choose either path.

4. Wait

If one of the city plans fits your lot and your budget is tight, waiting can be reasonable. Keep in mind that any change to a pre-approved plan triggers full plan review, the same as a custom ADU (form B-75), and that you must pick the style closest to your house's colors and materials.

How we'd decide

If you...We'd lean toward
Want to start this year and the lot is straightforwardCustom design, kept simple
Want attached, two-story or over-garageCustom design
Have a flat lot with easy crane accessCompare a factory-built unit
Have a tight budget and flexible timingSite work now, decide when the city plans return

We'll keep checking the program page and update our permit-ready plans guide when the status changes.

Sources, checked Oct 14, 2026: Permit-Ready ADU Program page · city ADU page · IB-111 (Aug. 2026).